Use the Gantt layout in PowerTable to visualize and manage project tasks on a timeline. You can track task duration and progress, manage milestones and dependencies, and monitor project schedules in a single view.
You can use the Gantt layout to:
In this article, you learn how to create and configure a Gantt layout for your table by using an example.
This example uses a Project Tasks table that stores project task details.

To create a Gantt layout, make sure the table meets the following requirements:


These are the optional fields you can set to leverage the complete Gantt chart capabilities.
Hierarchy type
The hierarchy type organizes the task list into parent tasks and subtasks. You can organize tasks into a parent-child hierarchy by using either Parent ID or Hierarchy By.


Milestone
Under Milestone, select the date column that identifies important events or deadlines, if available.
If your data doesn't include a separate milestone field, PowerTable identifies milestones based on the Start Date and End Date fields. A task is treated as a milestone when it has only an End Date or when the Start Date and End Date are the same.
Progress
Under Progress, select the numeric column that contains the task completion percentage.
Dependency
Under Dependency, select the column that contains task dependency information. Use the TaskID-ConnectionType format to define dependencies. For example, 1002FS indicates that the current task starts after task 1002 finishes. Supported dependency types include Finish-to-Start (FS), Start-to-Start (SS), Start-to-Finish (SF), and Finish-to-Finish (FF).

Estimated Effort
In Estimated Effort, select the field that contains the estimated effort for each task in hours.
Filter Columns
Select the columns that you want to make available for filtering in the Filter side panel. If no columns are selected, all columns are available for filtering.
PowerTable displays the tasks in the Gantt layout.